Water Systems Improvements Phase I and II

SUmmary

Utility Improvements, Drinking Water System

Phase I consisted of the construction of the Cimarron River water diversion structure, the installation of a "wet well", the new water tank and pump house, and the concrete pipe water distribution lines to transport water from the river to the storage tank on the hill.

Phase II involved the installation of 27,900 feet of new water transmission lines, connecting from the old Cimarroncita distribution lines to the water storage tank.

Checklist

  • Booster Station
  • Concrete
  • Dewatering
  • Earthwork
  • Flexible Pipe
  • Gabions
  • Masonry
  • Pumps
  • PVC Pipe
  • RCP
  • Seeding
  • Shot Creet
  • Steel Tank
  • Telemetry System
  • Water diversion structures